Nev. Admin. Code § 445A.232

Current through December 12, 2024
Section 445A.232 - Fees
1. A nonrefundable application fee must accompany each original application for a permit, each application for a modification to a permit, other than a minor modification made pursuant to NAC 445A.263, and each application to renew a permit which is submitted to or required by the Director. Except as otherwise provided in subsections 6 and 8, the Director shall charge the following fees:

Type of Permit Issued

Application Fee

Fee for Annual Review and Services

DISCHARGE OF DOMESTIC WASTEWATER

Less than 50,000 gallons daily ............................

$1,000

$1,406

50,000 gallons or more but less than 250,000 gallons daily ..........................................

1,500

2,109

250,000 gallons or more but less than 500,000 gallons daily .................................................................

2,000

2,812

500,000 gallons or more but less than 1,000,000 gallons daily ..............................................................

3,000

4,219

1,000,000 gallons or more but less than 2,000,000 gallons daily ..............................................................

4,000

5,626

2,000,000 gallons or more but less than 5,000,000 gallons daily ..............................................................

6,000

8,438

5,000,000 gallons or more but less than 10,000,000 gallons daily ...........................................................

10,000

14,066

10,000,000 gallons or more but less than 20,000,000 gallons daily ..........................................................

10,000

28,132

20,000,000 gallons or more but less than 40,000,000 gallons daily ..........................................................

10,000

42,198

40,000,000 gallons or more daily .............................................

10,000

56,263

DISCHARGE OF RECLAIMED WATER OTHER THAN THROUGH A SPREADING BASIN

Less than 50,000 gallons daily .................................................

$750

$1,055

50,000 gallons or more but less than 250,000 gallons daily ...............................................................

1,000

1,406

250,000 gallons or more but less than 500,000 gallons daily .................................................................

1,250

1,758

500,000 gallons or more but less than 1,000,000 gallons daily ..............................................................

1,500

2,109

1,000,000 gallons or more but less than 10,000,000 gallons daily ............................................................

2,000

2,812

10,000,000 gallons or more but less than 20,000,000 gallons daily ............................................................

2,500

3,516

20,000,000 gallons or more but less than 40,000,000 gallons daily ............................................................

3,000

4,219

40,000,000 gallons or more daily ...........................................

3,500

4,923

DISCHARGE OF RECLAIMED WATER THROUGH A SPREADING BASIN

Less than 10,000,000 gallons daily ........................................

$10,000

$14,066

10,000,000 gallons or more but less than 20,000,000 gallons daily ........................................................

10,000

28,132

20,000,000 gallons or more but less than 40,000,000 gallons daily ........................................................

10,000

42,198

40,000,000 gallons or more daily ...........................................

10,000

56,263

DISCHARGE FROM REMEDIATION, DEWATERING, OTHER THAN A DISCHARGE TO GROUNDWATER FROM THE DEWATERING OF A MINE, OR FROM A POWER PLANT, A MANUFACTURING OR FOOD PROCESSING FACILITY OR ANY OTHER COMMERCIAL OR INDUSTRIAL FACILITY

Cooling water only ............................................................

$2,000

$2,812

Less than 50,000 gallons of process water daily .........................................................................

2,500

3,516

50,000 gallons or more but less than 250,000 gallons of process water daily .....................................

3,000

4,219

250,000 gallons or more but less than 500,000 gallons of process water daily .....................................

4,000

5,626

500,000 gallons or more but less than 1,000,000 gallons of process water daily ..................................

5,000

7,032

1,000,000 gallons or more but less than 2,000,000 gallons of process water daily ..................................

6,000

8,438

2,000,000 gallons or more but less than 5,000,000 gallons of process water daily ..................................

8,000

11,252

5,000,000 gallons or more but less than 10,000,000 gallons of process water daily ................

10,000

14,066

10,000,000 gallons or more but less than 20,000,000 gallons of process water daily ................

10,000

28,132

20,000,000 gallons or more but less than 40,000,000 gallons of process water daily ................

10,000

42,198

40,000,000 gallons or more of process water daily .................................................................

10,000

56,263

DISCHARGE FROM A TREATMENT PLANT FOR DRINKING WATER

Intermittent discharge of less than 100,000 gallons daily ...................................................................

$500

$703

Intermittent discharge of 100,000 gallons or more but less than 1,000,000 gallons daily ....................

750

1,055

Intermittent discharge of 1,000,000 gallons or more daily ......................................................................

1,000

1,406

Routine discharge of less than 100,000 gallons daily ...................................................................

500

703

Routine discharge of 100,000 gallons or more but less than 1,000,000 gallons daily .............................

750

1,055

Routine discharge of 1,000,000 gallons or more daily .................................................................

1,000

1,406

DISCHARGE OF WASTEWATER FROM A CONCENTRATED ANIMAL FEEDING OPERATION

Less than 100,000 gallons daily ................................

$1,500

$2,109

100,000 gallons or more but less than 500,000 gallons daily ................................................

2,000

2,812

500,000 gallons or more daily ...................................

2,500

3,516

PERMIT FOR A CONCENTRATED ANIMAL FEEDING OPERATION THAT DOES NOT DISCHARGE WASTEWATER

Area of a holding facility that is less than 10 acres..........

$1,500

$2,109

Area of a holding facility that is 10 acres or more but less than 20 acres .......................................................

2,000

2,812

Area of a holding facility that is 20 acres or more .............................................................................

2,500

3,516

DISCHARGE FROM A FISH HATCHERY

Less than 500,000 gallons daily ..............................

$750

$1,055

500,000 gallons or more but less than 2,500,000 gallons daily ...........................................

1,000

1,406

2,500,000 gallons or more daily ..............................

1,500

2,109

OTHER PERMITTED DISCHARGES

Less than 50,000 gallons daily ................................

$1,000

$1,406

50,000 gallons or more but less than 250,000 gallons daily ..............................................

1,500

2,109

250,000 gallons or more but less than 500,000 gallons daily ...............................................

3,000

4,219

500,000 gallons or more but less than 1,000,000 gallons daily ............................................

5,000

7,302

1,000,000 gallons or more but less than 10,000,000 gallons daily ..........................................

10,000

14,066

10,000,000 gallons or more but less than 35,000,000 gallons daily ..........................................

10,000

28,132

35,000,000 gallons or more daily .............................

10,000

42,198

REUSE OF SEWAGE SLUDGE

Less than 20,000 cubic yards per year ...................

$1,500

$2,109

20,000 cubic yards or more per year ......................

3,000

4,219

REUSE OF DOMESTIC SEPTAGE .........................................

$1,000

$1,406

DISCHARGE FROM A RECREATIONAL LAKE .....................................

$5,000

$7,032

TEMPORARY PERMIT .......................................

$350

Not Applicable

2. A nonrefundable application fee must accompany each original application for a permit and each application to renew a permit for the discharges set forth in this subsection that is submitted to or required by the Director.

Except as otherwise provided in subsections 6 and 8, the Director shall charge the following fees:

Type of Discharge Permitted

Application Fee for Original Permit

Application Fee for Renewal of Permit

Fee for Annual Review and Services

RUNOFF OF STORM WATER

Industrial or commercial facility, including any structure, that is 5 acres to 10 acres, inclusive, in size ................................

$300

$150

$750

Industrial or commercial facility, including any structure, that is more than 10 acres but less than 25 acres in size ...........................

600

300

750

Industrial or commercial facility, including any structure, that is more than 25 acres in size ..............

1,000

500

750

Municipality whose population is 250,000 or less ..........................................

1,200

1,200

1,200

Municipality whose population is more than 250,000 .................................

2,000

2,000

2,000

3. Except as otherwise provided in subsection 8, a nonrefundable application fee of $150 must accompany each application for a minor modification made pursuant to NAC 445A.263.
4. To determine the number of acres of a holding facility for an application fee or a fee for the annual review and services for a permit issued to a concentrated animal feeding operation that does not discharge wastewater, the Director shall multiply the number of animals in the concentrated animal feeding operation by .0023.
5. An application fee or a fee for the annual review and services charged pursuant to subsection 1 must be based upon the limit of flow, in gallons per day, of the discharge authorized in the permit.
6. The application fee for a permit with a term of less than 5 years must be reduced by the Director in accordance with the term of the permit, but in no case may the fee be reduced by an amount equal to more than one-third of the fee set forth in this section.
7. If required, the fee for the annual review and services must be:
(a) Submitted to the Division on or before July 1 of each year; and
(b) Paid in advance for the period of review that relates to the fiscal year following payment.
8. For the fiscal year beginning on July 1, 2024, and for the fiscal year beginning on July 1, 2025, the Director shall increase each fee for the annual review and services set forth in subsection 1 by 10.33 percent of the fee for the immediately preceding fiscal year. For the fiscal year beginning on July 1, 2026, and for each fiscal year thereafter, the Director shall increase each of the following fees by 3 percent of the fee for the immediately preceding fiscal year:
(a) Each application fee set forth in subsections 1 and 3;
(b) Each fee for the annual review and services set forth in subsection 1;
(c) Each application fee for an original permit that applies to a discharge of runoff of storm water set forth in subsection 2;
(d) Each application fee for the renewal of a permit that applies to a discharge of runoff of storm water set forth in subsection 2;
(e) Each fee for the annual review and services that applies to a discharge of runoff of storm water set forth in subsection 2; and
(f) Each fee for a minor modification set forth in subsection 3.

In establishing any fee pursuant to this subsection, the Director shall round to the nearest dollar.

9. The Director may, during any fiscal year, suspend an increase in a fee.
10. The Director shall post on the Internet website of the Division the fees required pursuant to this section that are applicable to each fiscal year.
11. The Director may allow a holder of a permit to pay any fee required by subsection 1 pursuant to a payment plan if the holder of the permit submits a petition to the Division, on a form prescribed by the Division, which demonstrates that the payment of the fee in a lump sum would cause financial hardship to the holder of the permit.
12. As used in this section:
(a) "Concentrated animal feeding operation" has the meaning ascribed to it in 40 C.F.R. § 122.23.
(b) "Domestic septage" has the meaning ascribed to it in 40 C.F.R. § 503.9.
(c) "Sewage sludge" has the meaning ascribed to it in 40 C.F.R. § 503.9.

Nev. Admin. Code § 445A.232

Environmental Comm'n, Water Pollution Control Reg. §§ 2.2.5-2.2.5.2, eff. 5-2-78-NAC A 12-3-84; 7-22-87; 9-1-89; 9-19-90; 9-25-90; 9-13-91; 3-27-92; 10-29-97, eff. 7-1-2001; R206-99, 1-26-2000, eff. 7-1-2001; R063-04, 10-6-2004; R138-06, 9-18-2006; A by R101-16A, eff. 12/21/2016; A by R018-20A, eff. 8/26/2020; A by R112-22A, eff. 12/29/2022; A by R137-24A, eff. 10/23/2024

NRS 445A.425, 445A.430