Within 30 days after completing construction on a new process component or monitoring system specified in the permit or materially modifying an existing process component or monitoring system specified in the permit, the holder of the permit shall submit a report to the Department for review and approval which must include, without limitation:
1. As-built drawings of the process component or monitoring system specified in the permit and identification of any deviations from the previously approved design;2. A summary of the quality assurance and quality control procedures which were carried out during construction and the associated test results;3. The final operating plans required by NAC 445A.398 which have been revised to reflect modifications made during construction, including, without limitation, any necessary updates to the tentative plan for permanent closure of the facility; and4. The locations of all monitoring points set forth in the permit, which must be expressed in meters and decimals of meters, using the Nevada Coordinate System of 1983 in accordance with the requirements of chapter 327 of NRS.Nev. Admin. Code § 445A.427
Added to NAC by Environmental Comm'n, eff. 9-1-89-Substituted in revision for NAC 445.24348; A by R018-20A, eff. 8/26/2020