Nev. Admin. Code § 445A.6764

Current through October 11, 2024
Section 445A.6764 - Submission to Division of manual of operations and maintenance for water project

Not later than 90 days after a water project is completed, the recipient shall submit to the Division a draft of the manual of operations and maintenance for the water project required pursuant to NAC 445A.6667.

Nev. Admin. Code § 445A.6764

Added to NAC by Bd. of Health by R067-98, eff. 7-23-98; A by Environmental Comm'n by R128-04, 2-14-2005

NRS 445A.270