Nev. Admin. Code § 445A.67571

Current through October 11, 2024
Section 445A.67571 - Priority list: Submission for approval; objections to ranking of water projects
1. After the Division holds a public participation workshop, if such a workshop is required pursuant to NAC 445A.67568, and at least 3 working days before the meeting of the Board for Financing Water Projects, the Division shall submit the priority list to the Board for review and possible approval.
2. Any objection to the proposed priority list that is not resolved by the Division before the meeting of the Board for Financing Water Projects may be made orally at the meeting of the Board.
3. A priority list becomes finalized after approval by the Board for Financing Water Projects.

Nev. Admin. Code § 445A.67571

Added to NAC by Bd. of Health by R067-98, eff. 7-23-98; A by R099-14, eff. 10/24/2014; A by R109-22A, eff. 12/29/2022

NRS 445A.270