Section 408.323 - Completion of relocation of facility
The relocation of the utility's facility must be completed:
1. By the employees of the utility;2. Pursuant to a contract administered by the utility;3. Pursuant to a contract administered by the Department; or4. Any combination of subsections 1, 2 and 3.
Nev. Admin. Code § 408.323