Nev. Admin. Code § 338.360

Current through June 11, 2024
Section 338.360 - "Successfully completed project" defined

"Successfully completed project" means that the construction or the portion of the construction for which the subcontractor was responsible was completed:

1. Within the deadline for completion specified in the contract, as adjusted by any change order or extension of time granted; and
2. In compliance with any remaining contractual requirements, including close-out documents, within 90 days after substantial completion of the contract.

Nev. Admin. Code § 338.360

Added to NAC by Pub. Works Bd. by R095-04, eff. 12-15-2004

NRS 338.1376