Nev. Admin. Code § 338.530

Current through June 11, 2024
Section 338.530 - Procedure for selection of most qualified applicants
1. The Administrator of the Division shall appoint a ranking panel in accordance with the provisions of subsection 1 of NRS 338.1693. In the manner set forth in subsection 2 of NRS 338.1693, the ranking panel shall rank each proposal submitted by an applicant who satisfies the criteria set forth in NRS 338.1691 and NAC 338.500 for qualifying to enter into a contract with the Division for preconstruction services and to construct a public work.
2. After a ranking panel has ranked proposals pursuant to subsection 1, the Administrator must:
(a) Select at least the two but not more than the five applicants whose proposals received the highest scores for interviews. If the Division did not receive at least two proposals from applicants who satisfy the criteria set forth in NRS 338.1691 and NAC 338.500 for qualifying to enter into a contract with the Division for preconstruction services and to construct a public work, the Division may not enter into a contract with a construction manager at risk.
(b) Notify each applicant selected for an interview that the applicant has been selected for an interview.
(c) Request that each applicant selected for an interview submit to the Administrator a proposed amount of compensation for managing the preconstruction and construction of the public work. The Administrator must not disclose to the interview panel the information submitted pursuant to this paragraph until the interview panel has completed the interview process and assigned a preliminary score to each applicant.
(d) Appoint an interview panel consisting of at least three members, at least two of whom have experience in the construction industry, to interview the applicants. The Administrator may not appoint to the interview panel any person who was appointed to the ranking panel.
3. If, after ranking proposals pursuant to subsection 2 of NRS 338.1693, the ranking panel determines that fewer than two applicants satisfy the criteria set forth in NRS 338.1691 and NAC 338.500, the Division may not enter into a contract with a construction manager at risk.
4. An applicant selected for an interview pursuant to subsection 4 of NRS 338.1693 who qualifies for and wishes to receive from the interview panel the preference described in subsection 3 of NRS 338.1693 must provide to the interview panel:
(a) The applicant's certificate of eligibility to receive a preference in bidding on public works; and
(b) The affidavit for receiving a preference in bidding on public works which is prescribed by the Board.
5. The interview panel shall rank the proposals submitted by the applicants selected for interviews by evaluating and assigning a preliminary score to each proposal based on the factors and relative weight assigned to each factor that the Division specified in the request for proposals published pursuant to NAC 338.510. When ranking the interviewed applicants, the interview panel may not consider the score assigned to an applicant's proposal by the ranking panel.
6. After a preliminary score has been assigned to each applicant:
(a) The Administrator must provide to the interview panel each proposed amount of compensation for managing the preconstruction and construction of the public work which was requested pursuant to paragraph (c) of subsection 2, and the interview panel must:
(1) Calculate a score for the proposed amount of compensation by dividing the lowest of all the proposed amounts by the applicant's proposed amount multiplied by the total possible points available to each applicant; and
(2) Adjust appropriately each applicant's preliminary score to include the score calculated for the proposed amount of compensation. In adjusting each applicant's preliminary score pursuant to this subparagraph, the proposed amount of compensation must not exceed 20 percent of the final score of each applicant.
(b) Except as otherwise provided in this paragraph, the interview panel shall assign a relative weight of 5 percent to the possession of a certificate of eligibility to receive a preference in bidding on public works, if the applicant has submitted the information required by subsection 4 and is qualified to receive the preference. If any federal statute or regulation precludes the granting of federal assistance or reduces the amount of that assistance for a particular public work because of the provisions of this paragraph, the provisions of this paragraph do not apply insofar as their application would preclude or reduce federal assistance for the public work. The interview panel may assign the preference described in this paragraph only after all other scoring is complete and only if the assignment of the preference will determine the outcome of the selection of the construction manager at risk.
7. As used in this section:
(a) "Interview panel" means a panel appointed by the Administrator of the Division to interview applicants who have submitted proposals pursuant to subsection 3 of NRS 338.1692 and have been selected for interviews by the public body or its authorized representative pursuant to subsection 4 of NRS 338.1693.
(b) "Ranking panel" means a panel appointed by the Administrator of the Division to rank proposals in accordance with the provisions of subsection 2 of NRS 338.1693.

Nev. Admin. Code § 338.530

Added to NAC by Pub. Works Bd. by R098-11, eff. 5-30-2012

NRS 341.070, 341.110