Nev. Admin. Code § 211.120

Current through June 11, 2024
Section 211.120 - Plan review of proposed construction or alteration
1. Plans and specifications for alteration or new construction of any local correctional institution must be submitted to the appropriate health authority for review before work is begun.
2. Where a city, county or district health department is operated full time, plans and specifications must be submitted to that department for review before work is begun.
3. All such plans and specifications must:
(a) Show the layout of the building;
(b) Show the types of material to be used in the construction;
(c) Show the size and location of the fixed equipment and facilities; and
(d) Include complete plans for the plumbing, electrical and mechanical systems, with details for the heating, ventilating and cooling installations.
4. The appropriate health authority shall not grant final approval for alteration or construction until it has been approved by the local building and fire officials.

Nev. Admin. Code § 211.120

Bd. of Health, Jails and Local Correctional Institutions, §§ 18.1, 18.2, 18.3 & 18.4, eff. 6-13-80

NRS 444.335