The amount actually disbursed for a program or project, or a separable component of a project, shall not exceed the dollar amount of the tentative allocation for the program, project or separable component approved by the Commission pursuant to section 4-001 or a dollar amount equal to the same percentage of the actual project costs as the tentative allocation represented to the estimated project costs, whichever is less, without specific Commission approval; except that funds apportioned and set aside for one separable component but not disbursed may be used to reimburse the Sponsor for the costs of another separable component even though such reimbursement may exceed the amount apportioned and set aside for that component if necessary in accordance with section 4-002 to achieve or maintain the appropriate ratio between eligible project costs paid by the Sponsor and those paid by the Department.
256 Neb. Admin. Code, ch. 4, § 012