The Department will consider approval for location of closed loop heat pump wells at closer proximity than 1,000 feet horizontal separation distance, when the licensed professional engineer or licensed professional geologist representing the owner(s) of the closed loop heat pump wells, demonstrates to the Director or Director's designee that such location will not constitute a pollution hazard to the safety of the water supply, and that the owner(s) of the community water system has no objection to the location of the closed loop heat pump wells.
The engineer or geologist must submit the supporting data as appropriate to make a case for approval of the proposed location of heat pump wells to the Department 30 working days prior to the date on which action by the Director or Director's designee is desired. The contractor must not begin construction until the Department has approved the location.
178 Neb. Admin. Code, ch. 12, § 010