Current through September 17, 2024
A loadout facility is not needed under the following conditions:
003.01 When loadout activities are conducted at the application site as part of the normal application; or003.02 When custom applicator loadout activities are conducted no more than fourteen days in a calendar year at any one location, the custom applicator has a loadout facility at a primary operating location, and all other requirements are met. This fourteen day allowance does not apply to loadout facilities required in conjunction with secondary containment specified in 001.01 above or to loadout facilities specified in 001.04 above.198 Neb. Admin. Code, ch. 3, § 003
Amended effective 12/10/2019Amended effective 4/25/2020