Current through September 17, 2024
Section 124-3-004 - Construction and Operating Permit Application004.01 The construction permit and the operating permit for a single system are covered by one application.004.02 The owner of a dwelling or non-dwelling facility will submit a complete permit application on a form provided by the Department and include any supporting documents or reports requested.004.03 The plans, specifications, reports, and other technical documents submitted as part of the application will be prepared and properly stamped and signed by a Professional Engineer.004.04 The Department may require additional information to ensure proper engineering design and operation. 004.05 The permit application fee (see Appendix A) is to be submitted to the Department with the application. For subdivisions, a fee will be due for each lot subject to approval.124 Neb. Admin. Code, ch. 3, § 004
Amended effective 6/27/2022