Current through September 17, 2024
The abandonment of mechanical WWTF and pumping stations will be completed in the following manner:
005.01 The facility will be emptied of wastewater, grit, sludge, and other wastewater residues. All wastewater and solids will be disposed in accordance with applicable regulations.005.02 Hazardous chemicals will be removed from the site.005.03 Pumps, comminutors, blowers, and other mechanical equipment will be removed from the site.005.04 The structure of manholes, wet wells, and other deep confined basins will be removed to at least three feet below grade and filled with compacted soil. 123 Neb. Admin. Code, ch. 10, § 005