110 Neb. Admin. Code, ch. 10, § 5

Current through September 17, 2024
Section 110-10-5 - The Practice of Engineering and Architecture
10.5.1 The development and utilization of construction means and methods such as schedules, work plans, work orders and directions, procedures, construction calculations, selection, provision and use of temporary facilities in support of construction activities, reports, selection and use of safety procedures and facilities, instructions and similar items customarily used by contractors to implement construction work designed by licensed persons does not constitute the practice of engineering or architecture.
10.5.2 The preparation by employees of construction companies of ancillary drawings and data, such as field details, shop drawings, product data, conceptual drawings, calculations, diagrammatic instructions and similar documents and information, which are typically utilized to implement the construction of a facility designed by a licensed person does not constitute the practice of engineering or architecture.
10.5.3 The performance of field layout and installation work by employees of construction companies on projects designed by a licensed person or persons, including construction work such as field staking and measurement; installation of material or equipment at designed locations or locations selected in the field; field fitup and modification work; and layout of construction installation and support work does not constitute the practice of engineering or architecture.
10.5.4 The estimate of the cost of construction work (including the extent of the cost of changes in the work) by construction companies including such things as preparing and reviewing preliminary concepts of the project, identifying the scope of the construction work, preparing preliminary schedules and sequences for the construction work, and evaluating the estimates of subcontractors and suppliers, does not constitute the practice of engineering or architecture.
10.5.5 The performance of work customarily involved in project management of construction work on projects designed by licensed persons does not constitute the practice of engineering or architecture. Examples would be:
10.5.5.1 The evaluation of the project and its budget;
10.5.5.2 Services relating to financing the project;
10.5.5.3 Recommendations on construction feasibility, timing of design and construction, and factors relating to construction costs such as alternative designs prepared by a licensed professional;
10.5.5.4 Procurement of labor and materials;
10.5.5.5 Coordination and evaluation of subcontractor performance;
10.5.5.6 Preparation of schedules;
10.5.5.7 Estimating the project costs;
10.5.5.8 Performing construction work; and
10.5.5.9 Reporting on the progress and costs of the work.
10.5.6 Preliminary and Final Plats Preparation of a preliminary plat is not restricted, but the final plat must be prepared and certified by a registered Land Surveyor. If, however, the final plat contains streets (other than rights-of-way), sewers, water lines, or other engineering works, it needs to be prepared and certified by both a registered Land Surveyor and a professional engineer. Mathematical details of the final plat are the responsibility of the registered Land Surveyor. Physical details, such as grading, public works, or construction are the responsibility of the professional engineer and may not be certified by the registered Land Surveyor.
10.5.7 Livestock Waste Permits; Neb. Rev. Stat. §§ 81-3449(13) & 81-3453(12)

Under the E&A Act, the seal of an architect or professional engineer will be required for work related to livestock waste facilities only when the work falls within the definition of practice of architecture (Neb. Rev. Stat. § 81-3420) or practice of engineering (Neb. Rev. Stat. § 81-3421).

10.5.8 Water Based Fire Protection Systems; Neb. Rev. Stat. §§ 81-3449 (11) & 81-3453 (7)

Nothing in the E&A Act prevents a certified water-based fire protection system contractor with a responsible managing employee from engaging in the business of installation, repair, alteration, addition, maintenance, or inspection of water-based fire protection systems, or system layout recognized by the State Fire Marshal, in accordance with Neb. Rev. Stat. §§ 81-5,158 to 81-5,164.

10.5.9 Participation in a Conceptual Design Competition

Participation in a conceptual design competition in Nebraska is not considered the practice of architecture or engineering.

10.5.10 Spill Prevention Containment and Countermeasures

Preparation of Spill Prevention Containment and Countermeasure (SPCC) plans for a project located in Nebraska that requires the seal of a professional engineer, constitutes the practice of engineering and must be prepared by a professional engineer licensed by the Board.

10.5.11 Forensic Engineering

Forensic testing requiring the services of an architect or professional engineer, for purposes of the Act, is considered the practice of architecture and/or engineering, regardless of where the test material originated, if the facility performing the testing services is located in Nebraska.

10.5.12 Expert Witness

An architect or professional engineer who serves as a testifying or non-testifying expert in a lawsuit or arbitration in the state of Nebraska regarding issues within the scope of their professional knowledge is not practicing architecture or engineering in Nebraska for purposes of the Act, and such service does not constitute the unauthorized practice of engineering or architecture if the expert is not licensed in this State.

110 Neb. Admin. Code, ch. 10, § 5

Amended effective 4/27/2019
Amended effective 6/7/2021
Amended effective 10/8/2022
Amended effective 3/16/2024