Current through September 17, 2024
Rule 12 - Temporary ServicesThe installer or electrical contractor must submit an application for State electrical inspection for the temporary service.
1. The inspection fee will be based on service capacity and number of branch circuits.2. The application must be submitted a minimum of five working days prior to the date energization is required.3. The State Electrical Inspector may verbally authorize energization following inspection if the installation is in compliance with the provisions of the National Electrical Code referenced in Section 81-2104(5) of the State Electrical Act.100 Neb. Admin. Code, tit. 100, Rule 12
Amended effective 12/27/2022