Mont. Admin. r. 18.4.201

Current through Register Vol. 21, November 2, 2024
Rule 18.4.201 - ALTERNATIVE CONTRACT PROJECT DELIVERY METHODS
(1) Construction manager general contractor experience will not be a required scoring criteria for highway construction projects.
(2) The department must weight the in-person interview of each shortlisted proposer as at least half of the technical score. The technical proposal will account for the balance of the technical score.

Mont. Admin. r. 18.4.201

NEW, 2023 MAR p. 705, Eff. 7/22/2023

AUTH: 60-2-201, 60-3-101, MCA; IMP: 60-2-111, 60-2-112, 60-2-134, 60-2-201, MCA; Ch. 145, L. 2023, Section 1