Rule 17.8.333 - EMISSION STANDARDS FOR EXISTING ALUMINUM PLANTS - MONITORING AND REPORTING
(1) For the purpose of this rule the department adopts and incorporates by reference 40 CFR 60.195 update which sets forth test methods and procedures for primary aluminum reduction plants. A copy of this incorporated material may be obtained from the Department of Environmental Quality, P.O. Box 200901, Helena, MT 59620-0901.
(2) An owner or operator shall submit by May 1, 1982 to the department a detailed monitoring program including, but not limited to, a description of monitoring equipment, monitoring procedures, monitoring frequency, and any other information requested by the department. The monitoring program must be approved by the department and may be revised from time to time by the department.
(3) In order to be approved by the department, the monitoring plan must meet the requirements of 40 CFR 60.195 or equivalent requirements established by the department.
(4) An owner or operator of an existing primary aluminum reduction plant shall submit a quarterly emission report to the department, no later than 45 days following the end of the calendar quarter reported, in a format and reporting parameters as requested by the department.