Mo. Code Regs. tit. 7 § 10-24.050

Current through Register Vol. 49, No.12, June 17, 2024
Section 7 CSR 10-24.050 - Types of Projects in Which Design-Build Contracting May Be Used

PURPOSE: This rule provides for the design-build method used in determining a project "qualified" and how it applies to Intelligent Transportation System (ITS) projects.

(1) Subject to the provisions of 227.107, RSMo , the design-build contracting technique may be used for any project which the commission deems to be appropriate on the basis of project delivery time, cost, construction schedule, and/or quality.

7 CSR 10-24.050

AUTHORITY: sections 226.020, RSMo 2000 and 226.030 and 227.107, RSMo Supp. 2004.* Original rule filed Aug. 15, 2005, effective Feb. 28, 2006.
Amended by Missouri Register June 15, 2018/Volume 43, Number 12, effective 7/31/2018

*Original authority: 226.020, RSMo 1939; 226.030, RSMo 1939, amended 1965, 2003, 2004; and 227.107, RSMo 2002.