Mo. Code Regs. tit. 10 § 20-6.080

Current through Register Vol. 49, No.12, June 17, 2024
Section 10 CSR 20-6.080 - Signatures for Construction Permits, Operating Permits and Groundwater Heat Pump Injection/Withdrawal Wells

PURPOSE: This rule sets forth the authorization for the director of the Department of Natural Resources, in his/her capacity of administering Department of Natural Resources program, to delegate the review, reevaluation and approval/denial of construction permits, operating permits and permits to withdraw/inject water from/into subsurface wells.

(1) It is the responsibility of the Department of Natural Resources (DNR) to issue or deny Clean Water Commission permits. Authority to issue/deny Clean Water Commission permits rests with the director of DNR acting in his/her capacity of administering DNR programs. This authority may be delegated by letter from the director of the DNR to his/her designee. Denial of a Clean Water Commission permit will be by a certified letter that states-
(A) The permit is being denied;
(B) The reason(s) that the permit is being denied;
(C) Any action that the permittee could take to mitigate the denial and eventually secure the permit; and
(D) The permittee's right to appeal the staff denial to the Clean Water Commission within thirty (30) days.

10 CSR 20-6.080

AUTHORITY: section 644.026, RSMo Supp. 1987.* Original rule filed Jan. 13, 1981, effective May 11 , 1981.

*Original authority: 644.026, RSMo 1972, amended 1973, 1987.