39 Miss. Code. R. 4-I-6-110

Current through December 10, 2024
Section 39-4-I-6-110

If the DGF is not approved under a Level 2 review, the EU shall provide the Interconnection Customer a letter explaining its reasons for denying the Interconnection Request. The Interconnection Customer may submit a new Interconnection Request for consideration under a Level 3 interconnection review. The Queue Position assigned to the Level 2 Interconnection Request shall be retained provided the request is made within 15 business days of notification that the current Interconnection Request is denied.

39 Miss. Code. R. 4-I-6-110

Adopted 1/3/2016
Amended 8/12/2022
Amended 11/6/2022