Current through December 10, 2024
The Level 1 Interconnection Review shall then be conducted in accordance with the following procedures:
1. An EU shall, within 10 business days after receipt of the Interconnection Request, inform the Interconnection Customer in writing or by electronic mail that the Interconnection Request is complete or incomplete and indicate what, if any, materials are missing.2. When an Interconnection Request is complete, the EU shall assign a Queue Position.3. The EU shall, within 15 business days after notifying a Level 1 applicant that the application is complete, indicate that the DGF equipment meets all Level 1 criteria, verify the DG can be interconnected safely and reliably using Level 1 screens, and provide a conditionally approved Level 1 Interconnection Application Form and Agreement to the Interconnection Customer.39 Miss. Code. R. 4-I-5-102