39 Miss. Code. R. 4-I-2-105

Current through December 10, 2024
Section 39-4-I-2-105 - "Commissioning Tests"

"Commissioning Tests" means the tests applied to a DGF by an Interconnection Customer after construction is completed to verify that the DGF does not create Adverse System Impacts. At a minimum, the scope of the Commissioning Tests performed shall include the commissioning test specified by IEEE Standard 1547 section 5.4 "Commissioning Tests."

39 Miss. Code. R. 4-I-2-105

Adopted 1/3/2016
Amended 8/12/2022
Amended 11/6/2022