SCHEDULE
For periodic testing of watt-hour meters and curve drawing and integrating demand meters.
Rated Capacity of Meter | To be tested at least once in every..... |
Alternating Current Meters: | |
(1)Single Phase: Exceeding 50 amperes | 60 months |
50 amperes | 120 months1 |
(2) Polyphase: Exceeding 50 kilovolt amps | 60 months |
50 amperes or less | 60 months |
SCHEDULE
For periodic testing of lagged-demand meters2 | |
(1) Proportional timing | 4 years |
(2) Exponential timing | 5 years |
1 This time may be extended to 180 months provided meters purchased prior to January 1, 1937, are tested at least once in every ninety (90) months.
2 When combined with the kilowatt hour meter the demand meter may, at the option of the utility, be tested at the same time and interval as the associated kilowatt hour meter.
39 Miss. Code. R. 3-2-23