Rule 210.3: 019-020 ITS Protest Policy and Procedures
protest is finally resolved and the Protestor furnishes ITS with written notification that no appeal will be pursued.
Specifications were unduly restrictive and failed to promote fair and open competition
State failed to follow procedures established in the RFP or Letter of Configuration, ITS procurement policy and procedures, or ITS governing law
State failed to follow procedures established in the RFP or Letter of Configuration, ITS procurement policy and procedures, or ITS governing law
Scope and intent of the project as specified in the executed contract differ materially from the scope and intent of the RFP or Letter of Configuration
* Within five (5) Working Days after the date of the Official Release of the RFP; or
* Within two (2) Working Days before the Letter of Configuration response is due.
* Within five (5) Working Days after the Protestor knows or should have known of the failure to follow procedure, but in no event later than ten (10) Working Days after the Award of Contract.
* Within five (5) Working Days after the Protestor knows or should have known of the Disclosure of Information, but in no event later than ten (10) Working Days after the Award of Contract.
* All protests filed during this period must be preceded by a Post Procurement Review. (See Section 212.4: 021-0402(2)-Post Procurement Review-As Condition Precedent to Protest.)
* In order to preserve Protestor's right to protest, Protestor must request, in writing, a Post Procurement Review within five (5) Working Days of ITS's Notice of the Award of Contract.
* All protests must be filed within five (5) Working Days after Post Procurement Review. (For exceptions to this rule see Miss. Code Ann. Section 25-61-5(1)(b)).
* Within five (5) Working Days of the execution of the contract by the last signatory.
* Correct errors and re-evaluate all proposals; or
* Reissue the RFP or Letter of Configuration; or
* Make other findings and determine other courses of action as appropriate; or
36 Miss. Code. R. 2-10-210.3