33 Miss. Code. R. 2-3.4.1

Current through June 25, 2024
Rule 33-2-3.4.1

Upon determination by the Department that (a) all applicable requirements of the DWSIRLF loan application have been met, (b) the facilities plan has been approved, (c) the project is on the current year's priority list, and (d) funds are available for the amount of the DWSIRLF loan application, the Board Chairman or his designee will execute and transmit a DWSIRLF loan offer to the loan recipient. In addition to the estimated allowable project costs as described in Appendices A and B of these regulations, the loan offer may include a construction contingency, as determined by the Department, in the project budget.

33 Miss. Code. R. 2-3.4.1

Miss. Code Ann. § 41-3-16(3)(b)
Amended 7/31/2016
Amended 5/25/2017