This Appendix sets forth the process for the resolution of procurement protests filed with the loan recipient by an adversely affected party. The Loan Recipient's protest procedures must include the requirements of this Appendix.
(1) Prior to advertisement for bids, the loan recipient must establish its own procedures for prompt consideration of initial protests concerning solicitations or contract awards. A "protest" is a written complaint concerning the loan recipient's solicitation or award of a contract. The protest must be filed with the loan recipient by a party with a direct financial interest adversely affected by a loan recipient's procurement action and must be filed in accordance with and within the time frame established by the loan recipient's protest procedures.
(2) Any party who transmits any document concerning the protest during the course of a protest and protest resolution must simultaneously furnish all other affected parties and the Department with a copy of all documents in the transmittal.
(3) Upon receipt of a protest, the loan recipient must make a determination on the protest in accordance with the loan recipient's protest procedures within thirty (30) calendar days after such protest, or sooner if so required by the loan recipient's procurement protest procedures.
(4) The party with a direct financial interest adversely affected by a loan recipient's determination of the protest may appeal such a determination only through the appropriate court of competent jurisdiction, provided such appeal is initiated within seven (7) calendar days after receipt of the determination.
(5) Any delay due to a protest or protest resolution will not relieve the loan recipient of the requirement to meet the project schedule established in the loan agreement, nor will such delays prevent the Department from pursuing the remedies for default established in the loan agreement.
Miss. Code. tit. 33, pt. 2, ch. 3, app 33-2-3-L