15 Miss. Code. R. 10-76-2.1.3

Current through October 31, 2024
Rule 15-10-76-2.1.3

Pressure Piping -- (including welded piping) -- Piping external to power boilers from the boiler to the first stop valve of a single boiler, and to the second stop valve in a battery of two or more boilers is subject to the requirements of ASME Power Boiler Code, Section I, and the design, fabrication, installations and testing of the valves and piping shall be in conformity with the applicable paragraphs of ASME Code. Applicable ASME Data Report Forms for such piping shall be furnished by the owner to the Chief Inspector.

15 Miss. Code. R. 10-76-2.1.3

Miss. Code Ann. § 45-23-9