12 Miss. Code. R. 3-2.1-700.16

Current through January 14, 2025
Section 12-3-2.1-700.16 - CONSTRUCTION TESTING

Any soil investigations conducted by the Professional during the Planning Phase may be examined at the Professional's office by the Contractor for information purposes only and is not a Warranty of subsurface conditions. The Contractor may make his own investigations to satisfy himself with the site and subsurface conditions prior to bidding and at his own cost. Further, the Contractor will bear all cost of testing, inspections, etc. during the Construction Phase.

12 Miss. Code. R. 3-2.1-700.16

Amended 8/14/2016