Current through December 10, 2024
Section 12-3-2.1-1-01311-1.06 - SUBMITTALS FOR REVIEWA. Preliminary Network Diagram: Within fifteen (15) days after the date established in the Notice to Proceed submit proposed preliminary network diagram defining planned operations for the first sixty (60) days of Work, with a general outline for the remaining Work.B. Review: Participate in review of preliminary and complete network diagrams jointly with the Professional.C. Proposed Complete Network Diagram: Within twenty (20) days after joint review of proposed preliminary network diagram, submit draft of proposed complete network diagram for review. Include written certification that mechanical and electrical Subcontractors have reviewed and accepted proposed schedule.D. Complete Network Diagram: Within ten (10) days after joint review, submit complete network analysis consisting of network diagrams and mathematical analysis.E. Updated Network Schedules: Submit updated network schedules with each Application for Payment.F. Copies: Submit the number of opaque reproductions the Contractor requires, plus two (2) copies which will be retained by the Professional and the Owner.12 Miss. Code. R. 3-2.1-1-01311-1.06