Miss. Code. tit. 12, pt. 3, ch. 2, r. 12-3-2.1, div. 12-3-2.1-0, 12-3-2.1-0-00500, art. 12-3-2.1-0-00500-5-2

Current through December 10, 2024
Article 12-3-2.1-0-00500-5-2 - CONTRACT SUM
2.1 CONTRACT SUM
2.1.1 The Owner will pay the Contractor in current funds for the performance of the work, subject to additions and deductions by Change Order as provided in the Contract Documents, the Contract sum of _____________________________________________________________________________ Dollars ($ _________________________________). The Contract sum is determined as follows:

Base Bid $__________________
Modifications () Adds () Deducts $__________________
Negotiations $__________________
Alternate No. _____ () Adds () Deducts $__________________
Alternate No. _____ () Adds () Deducts $__________________
Alternate No. _____ () Adds () Deducts $__________________
Alternate No. _____ () Adds () Deducts $__________________
Alternate No. _____ () Adds () Deducts $__________________
Total Contract Sum $__________________

2.2LIQUIDATED DAMAGES
2.2.1 The stipulated liquidated damages described in Paragraph 9.11 of the Supplementary Conditions are in the amount of _________________________ _______________________________________________________ Dollars ($ ____________________________________) for each calendar day.

Miss. Code. tit. 12, pt. 3, ch. 2, r. 12-3-2.1, div. 12-3-2.1-0, 12-3-2.1-0-00500, art. 12-3-2.1-0-00500-5-2