Floodplain Permit Application Process
STEP | TIMELINE REQUIREMENT |
Floodplain Management Permit Application - STEP ONE form | Submit as soon as possible following initiation of project planning but in no case prior to advertisement of procurement. |
STEP TWO form | Due at least 15 calendar days prior to advertisement of procurement. |
Flood Development Initial Approval Letter | Sent by State Floodplain Manager with approval for all initial STEP TWO form documents/attachments. Sent within 15 days of receipt of documents/attachments. |
Flood Development Final Approval Letter | Sent by State Floodplain Manager with approval for all final STEP TWO form documents/attachments. Sent within 15 days of receipt of documents/attachments. |
Flood Development Denial Letter | Prepared by State Floodplain Manager for all unapproved projects within 15 days of receipt of all STEP TWO form and documents |
If FEMA has not defined the SFHA within a community (State of Mississippi), the community shall require permits for all proposed construction or other development in the community including the placement of manufactured homes, so that it may determine whether such construction or other development is proposed within flood-prone areas. Permits are required to ensure that proposed development projects meet the requirements of the NFIP and the community's floodplain management ordinance.
DFA, Office of State Property Insurance, State Floodplain Management website for Forms:
http://www.dfa.ms.gov/dfa-offices/state-property-insurance/forms/
12 Miss. Code. R. 10-200.3