Until such time as the State satisfies the Title II funding limitations described in Rule 4.2.G. of this regulation, all wastewater projects (as described in Section 212 of the Act) funded by the SRF must comply with the Title II requirements of Rule 4.2.G. and the crosscutting requirements in Appendix H. In addition, the following project requirements also apply:
Plans, specifications, and contract documents must also conform to such contract language, conditions, and forms as may be required by Department staff. The plans and specifications shall incorporate the accepted recommendations of any value engineering performed in accordance with this regulation. The plans, specifications, and contract documents must bear the seal of the registered professional engineer responsible for preparation of these documents.
An original and one copy of the SRF loan application shall be submitted to the Department staff. Only forms provided by the Department staff may be used, and they must not be altered. The SRF loan application may request assistance only for costs that are allowable in accordance with Appendices A and B of this regulation, and may include a construction contingency, as determined by the Department staff, in the project budget. The application amount shall include any administration fee charged to the loan recipient by the Department, as established in the Intended Use Plan under which the project is funded. A complete application shall conform to this regulation, including all Appendices, and shall include the following:
Prior to loan award, clear title certification forms from both the loan applicant and the Title Counsel must be submitted for all loan ineligible real property and easements (including poser and other utilities).
The loan recipient shall be responsible for assuring that every appropriate procedure and incidental legal requirement is observed in advertising for bids and awarding the construction contracts. The plans, specifications, and executed contract documents shall not vary from those approved by the Department staff.
The loan recipient shall arrange and hold a preconstruction conference and shall allow attendance and participation by the Department staff.
The Department staff is authorized to observe the building of any project at any time in order to assure that plans, specifications and contract documents are being followed and that the project is being built in accordance with sound engineering principles and building practices. A representative may be stationed at the building site by the Department staff to report on the manner and progress of the building or to report conditions relating to the equipment or materials furnished and the compliance by the contractor with approved plans, specifications and contract documents for the project. Such observation shall not subject the Department to any action for damages of other liability. Such observation will not release the contractor from any requirements of the contract documents or the consulting engineer from determining compliance with the requirements of the contract documents or the loan recipient rom insuring compliance with the terms of the loan agreement.
The contractor, consulting engineer and loan recipient shall furnish the Department staff with every reasonable facility for determining whether the work as performed is in accordance with the requirement and intent of the plans, specifications and contract documents. The Department staff is authorized to review and require submission of daily logs, record drawings, field notes, and any other document prepared by any party in relation to the SRF project.
All requests for change order approvals shall contain
Justification for contract time extensions included in a change order shall be prepared but need not be submitted to the Department unless the total time extensions for the contract exceed 25% of the original contract time, in which case justification for all time extensions shall be submitted to the Department for review and approval. Construction work which occurs after the date representing a 25% time extension to the original contract time is not allowable, unless approved as such by the Department staff pursuant to review of the justification for all time extensions.
11 Miss. Code. R. 6-4.3