The commissioner, using information furnished by the local units of governments from the statewide bridge inventory, must establish a statewide priority of bridge construction, reconstruction, or rehabilitation.
This priority must be based on the relative seriousness of each bridge's deficiencies as determined from the inventory and appraisal after considering the following criteria established in Minnesota Statutes, section 174.50, subdivision 6:
When the required documentation has been completed, construction plans are complete, and priorities have been established, the commissioner must notify the local units of government, as to funding availability from the Minnesota state transportation fund or federal funds.
The local unit of government must by resolution agree to the terms and conditions specified in the notification by the commissioner consistent with Minnesota Statutes, section 174.50, subdivision 5, clause (2).
Minn. R. agency 175, ch. 8810, BRIDGE CONSTRUCTION AND RECONSTRUCTION, pt. 8810.8400
Statutory Authority: MS s 174.50