Part 7105.0030 - GENERAL PROVISIONS
Subpart 1.Certification requirements and deadlines.

No person may install, repair, or close a tank system after July 9, 1990, unless:

A. a supervisor certified in the appropriate discipline is physically present on site at all critical junctures during the storage tank project; and
B. the certified supervisor in item A is also a certified contractor or is in the employ of a certified contractor.
Subp. 2.Certificate availability.

A copy of the contractor's current certificate must be at the work location and posted in a conspicuous place. Certified supervisors must have copies of current certificates issued by the agency at the location where they are supervising work.

Subp. 3.Tank owner or operator requirements.

Owners or operators of an underground storage tank must not allow a storage tank project to be performed on their tank system, except in compliance with subpart 1.

Minn. R. agency 167, ch. 7105, pt. 7105.0030

14 SR 1718

Statutory Authority: MS s 116.491