Owners or operators of industrial activities required to have an industrial storm water permit under part 7090.3010, subpart 1, must complete a storm water pollution prevention plan before submitting a permit application.
The storm water pollution prevention plan must be kept at the industrial facility and made available to the agency within 72 hours of a request for review.
Minn. R. agency 167, ch. 7090, pt. 7090.3040
Statutory Authority: MS s 115.03