Part 7090.2040 - CONSTRUCTION ACTIVITY MINIMUM REQUIREMENTS
Subpart 1.Storm water pollution prevention plan required.

Owners of construction activities required to have a construction storm water permit under part 7090.2010, subpart 1, must complete a storm water pollution prevention plan before submitting a permit application and before conducting construction activity.

Subp. 2.Record keeping.

The storm water pollution prevention plan must be kept on site and made available to the agency within 72 hours of a request for review.

Minn. R. agency 167, ch. 7090, pt. 7090.2040

30 SR 125