Part 7090.2010 - CONSTRUCTION ACTIVITY PERMIT REQUIREMENTS
Subpart 1.Permits required.

An NPDES/SDS construction storm water permit is required if:

A. a person is conducting construction activity; or
B. the commissioner determines that a discharge may cause or contribute to a violation of an applicable state or federal water quality rule or regulation. In making this determination, the commissioner shall consider factors including size of discharge, quantity and nature of discharge, and location of discharge.
Subp. 2.Permit application deadline.
A. Owners and operators proposing activities that require a construction storm water permit under this part must submit a complete permit application provided by the agency before conducting construction activity, or where a construction site is covered under an existing construction storm water permit, meet the subdivision registration requirements under part 7090.2060, if applicable.
B. The permit application or subdivision registration required under item A may be submitted electronically if such a method of submittal is approved by the commissioner. Notwithstanding the conditions of the construction storm water permit, the effective date of a permit under an electronic submittal must be established by the commissioner.
Subp. 3.Compliance requirements for unpermitted construction activity.

Owners and operators of construction activities required to have a construction storm water permit under this part that fail to submit a permit application or subdivision registration under subpart 2 shall comply with the storm water discharge design requirements, construction activity requirements, and the requirements of Appendix A in the construction storm water permit as incorporated by reference in part 7090.0060.

Minn. R. agency 167, ch. 7090, pt. 7090.2010

30 SR 125

Statutory Authority: MS s 115.03