This part and parts 7045.0602 to 7045.0606 apply to the owners and operators of all hazardous waste disposal facilities, including surface impoundments and waste piles from which the owner or operator intends to remove the wastes at closure, to the extent that the owner or operator is required to provide postclosure care in part 7045.0630, subpart 6, or 7045.0632, subpart 7; tank systems that are required under part 7045.0628, subpart 9, to meet the requirements for landfills; and containment buildings that are required under Code of Federal Regulations, title 40, section 265.1102, as incorporated in part 7045.0649, to meet the requirement for landfills, except as provided otherwise in part 7045.0552.
The postclosure plan must be submitted as follows:
A request for modification of the postclosure plan must be made to the commissioner at least 60 days before the proposed changes in operating plans or facility design, or no later than 60 days after the events which affect the postclosure plan occur. This request must include the revised postclosure plan and indicate the reasons for modifying the plan. The request must be made in accordance with subpart 3 and the commissioner shall take actions required in subpart 3. A modification to the plan will be approved in accordance with item D unless the modification meets the criteria of a minor modification in parts 7001.0190, subparts 2 and 3; and 7001.0730, subpart 4. The commissioner may request modifications to the postclosure plan under the conditions described in subitems (1) to (3). An owner or operator with an approved postclosure plan must submit the modified plan no later than 60 days after the commissioner's request. If an owner or operator of a surface impoundment or a waste pile who intended to remove all hazardous wastes at closure in accordance with part 7045.0630, subpart 6; or 7045.0632, subpart 7, is required to close as a landfill in accordance with part 7045.0638, subpart 4. The owner or operator must submit a postclosure plan within 90 days after the owner or operator or commissioner determines that the unit must be closed as a landfill.
The owner or operator also shall submit the plan to the commissioner no later than 15 days after: termination of interim status, except when a permit is issued to the facility simultaneously with termination of interim status; or issuance of a judicial decree or agency order to cease receiving waste or close.
The postclosure period may be modified during the postclosure care period as described in items A and B:
The commissioner shall provide the owner or operator and the public, through a newspaper notice, the opportunity to submit written comments or request a public information meeting within 30 days of the date of the notice. The commissioner shall in response to a request or at his or her own discretion hold a public information meeting whenever a meeting might clarify one or more issues concerning the postclosure plan. After considering the comments, a final determination shall be issued.
The commissioner shall base the final determination upon the criteria outlined in item A, subitem (1). A modification of the postclosure plan may include, when appropriate, the temporary suspension rather than permanent deletion of one or more postclosure care requirements. At the end of the specified period of suspension, the commissioner shall determine whether the requirements should be permanently discontinued or reinstated to prevent threats to human health and the environment.
Minn. R. agency 167, ch. 7045, INTERIM STATUS STANDARDS, pt. 7045.0600
Statutory Authority: MS s 116.07; 116.37