The owner or operator of the facility must send all submittals required under parts 7017.1002 to 7017.1220 to the agency in a physical or electronic format as specified by the commissioner and to the address identified on the required form or as provided by the agency.
Submittals must be postmarked or received by the date specified in the applicable regulation or compliance document.
All submittals, except for certification test-plans and relative accuracy test audits notifications, must be accompanied by a certification statement in a format specified by the commissioner and signed by a responsible official, pursuant to part 7007.0500, subpart 3.
Minn. R. agency 167, ch. 7017, CONTINUOUS MONITORING SYSTEMS, pt. 7017.1120
Statutory Authority: MS s 116.07