In the permit for a new hazardous waste thermal treatment facility, for the purpose of determining operational readiness following completion of physical construction, the commissioner shall establish permit conditions, including but not limited to, allowable waste feeds and operating conditions. These permit conditions are effective for the minimum time required to bring the thermal treatment facility to a point of operational readiness sufficient to conduct a trial burn, not to exceed 720 hours operating time for treatment of hazardous waste. The commissioner may extend the duration of this operational period once, for up to 720 additional hours, at the request of the applicant when good cause is shown. The permit may be modified to reflect the extension according to part 7001.0730, subpart 4, item H.
Applicants shall submit to the commissioner a statement, with Part B of the permit application, that suggests the conditions necessary to operate in compliance with the performance standards of part 7045.0542, subpart 4, during this period. This statement must include restrictions on waste constituents, waste feed rates, and the operating parameters identified in part 7045.0542, subpart 6.
The commissioner shall review this statement and other relevant information submitted with Part B of the permit application, and shall specify requirements for this period that are sufficient to meet the performance standards of part 7045.0542, subpart 4.
In the permit for a new hazardous waste thermal treatment facility, for the purposes of determining the feasibility of compliance with the performance standards of part 7045.0542, subpart 4, and of determining the adequate operating conditions under part 7045.0542, subpart 6, the commissioner shall establish permit conditions to be effective during the trial burn.
An applicant shall submit to the commissioner a trial burn plan with Part B of the permit application. The trial burn plan must include the following information:
The commissioner shall review the trial burn plan for completeness. If the commissioner finds that the trial burn plan is incomplete or otherwise deficient, the commissioner shall promptly advise the owner or operator of the incompleteness or deficiency. The commissioner shall suspend further processing of the trial burn plan until the owner or operator has supplied the necessary information or otherwise corrected the deficiency.
The commissioner shall designate as trial principal organic hazardous constituents those constituents for which destruction and removal efficiencies must be calculated during the trial burn. The commissioner's designations shall be based on the waste analysis data submitted by the owner or operator, the commissioner's estimate of the difficulty of thermally treating the hazardous constituents to be burned, and the concentration or mass of hazardous constituents in the proposed waste feed. In addition, if the waste analysis indicates that the waste feed contains wastes that are listed in part 7045.0135, then in making principal organic hazardous constituents determinations the commissioner shall consider the hazardous organic waste constituents identified in part 7045.0139 that formed the basis of this listing.
The agency shall approve a trial burn plan if the agency finds that:
The owner or operator shall conduct the trial burn in accordance with the trial burn plan approved by the agency. The owner or operator shall perform the following analyses or make the following determinations:
The owner or operator shall submit to the commissioner a certification that the trial burn has been carried out in accordance with the approved trial burn plan and shall submit the results of all the analyses and determinations required by subpart 6 along with all underlying data of the results. The owner or operator shall make these submissions within 90 days after the completion of the trial burn, or later if approved by the commissioner upon a finding by the commissioner that good cause exists for granting a time extension.
All submissions to the commissioner required by this rule must be signed in accordance with part 7001.0060 and must contain the certification required by part 7001.0540.
To allow a new hazardous waste thermal treatment facility to operate after completion of the trial burn and prior to final modification of the permit conditions to reflect the trial burn results, the commissioner shall establish permit conditions, including but not limited to allowable waste feeds and operating conditions sufficient to meet the requirements of part 7045.0542, subpart 6. The commissioner may prohibit the burning of hazardous wastes in the facility during this period. These permit conditions are effective for the minimum time required to complete sample analysis, data computation, and submission of the trial burn results by the applicant, and modification of the facility permit by the agency.
An applicant shall submit to the commissioner a statement with Part B of the permit application that identifies the conditions necessary to operate in compliance with the performance standards of part 7045.0542, subpart 4, during this period. This statement must include restrictions on waste constituents, waste feed rates, and the operating parameters identified in part 7045.0542, subpart 6.
The commissioner shall review this statement and other relevant information submitted with part B of the permit application and shall specify requirements for this period most likely to meet the performance standards of part 7045.0542, subpart 4.
To allow a new hazardous waste thermal treatment facility to operate after the commissioner reviews the results of the trial burn conducted under phase two, based on the results of the trial burn, the commissioner shall establish operating requirements in the final permit according to part 7045.0542. A permit modification, if necessary, must be completed according to part 7001.0730, subpart 2 or 4 and a permit revocation, if necessary, must be completed according to part 7001.0180, item C.
To determine the feasibility of compliance with the performance standards of part 7045.0542, subpart 4, and to determine adequate operating conditions under part 7045.0542, subpart 6, the applicant for a permit for an existing hazardous waste thermal treatment facility must prepare and submit to the commissioner a trial burn plan and perform a trial burn in accordance with subparts 3 to 8 and part 7001.0630, item B, or, instead, submit other information as specified in part 7001.0630, item C. Applicants submitting information under part 7001.0630, item A, are exempt from compliance with part 7045.0542, subparts 4 and 6, and, therefore, are exempt from the requirement to conduct a trial burn. An applicant who submits trial burn plans and who receives approval before submission of a permit application shall complete the trial burn and submit the results specified in subpart 6 with Part B of the permit application. Trial burn results must be submitted prior to issuance of the permit. If completion of this process conflicts with the date set for submission of the Part B application, the applicant shall contact the commissioner to establish a later date for the submission of the Part B application or trial burn results. When the applicant submits a trial burn plan with Part B of the permit application, the commissioner shall specify a time period prior to permit issuance in which the trial burn must be conducted and the results submitted.
Minn. R. agency 167, ch. 7001, HAZARDOUS WASTE FACILITY PERMITS, pt. 7001.0700
Statutory Authority: MS s 116.07; 116.37