Minn. R. agency 167, ch. 7001, GENERAL REQUIREMENTS, pt. 7001.0020

Current through Register Vol. 49, No. 24, December 9, 2024
Part 7001.0020 - SCOPE

Except as otherwise specifically provided, parts 7001.0010 to 7001.0210 apply to items A to H.

A. An agency permit required for the storage, treatment, processing, transfer, intermediate disposal, or final disposal of solid waste. Part 7001.0040 applies to permits for solid waste transfer facilities, recycling facilities, refuse-derived fuel processing facilities, and compost facilities, except that the time period referred to in part 7001.0040, subparts 1 and 3, shall be 90 days instead of 180 days.
B. An agency permit required for the treatment, storage, or disposal of hazardous waste.
C. An agency permit required for the treatment, distribution, utilization, storage, or disposal of sewage sludge.
D. An agency permit required for the construction, installation, or operation of a disposal system. Part 7001.0040, subparts 1 and 3, apply to permits for sewer extensions, except that the time period referenced in those subparts shall be 60 days instead of 180 days. Parts 7001.0100, subparts 4 and 5; 7001.0110; and 7001.0150 do not apply to permits for sewer extensions.
E. An agency permit required for the discharge of a pollutant into the waters of the state from a point source.
F. An agency permit required for the construction or operation of an animal feedlot or manure storage area or for the correction of a pollution hazard. However, parts 7001.0040, 7001.0050, 7001.0100, subparts 4 and 5, and 7001.0110 do not apply to animal feedlot interim and construction short-form permits issued under chapter 7020.
G. The processing of certifications under section 401 of the Clean Water Act, United States Code, title 33, section 1341, to the extent provided by parts 7001.1400 to 7001.1470.
H. An agency permit required for the construction or operation of a substance storage facility which:
(1) is a major facility as defined in part 7001.4205;
(2) stores:
(a) a substance as defined in part 7001.4205;
(b) asphalt; or
(c) fuel oil number 6; and
(3) is not an excluded aboveground storage tank system under part 7151.1300, subpart 2.

Part 7001.0040, subparts 1 and 3, apply to major facility substance storage permits except that the time period referenced in those subparts shall be 90 days instead of 180 days. Parts 7001.0100, subparts 4 and 5; 7001.0110; and 7001.0150 do not apply to these permits.

Part 7001.0080 applies to the permits in this item except that the time period referenced in part 7001.0080 shall be five years instead of three years.

Minn. R. agency 167, ch. 7001, GENERAL REQUIREMENTS, pt. 7001.0020

8 SR 2278; 10 SR 2235; 12 SR 1564; 12 SR 2513; 13 SR 1150; 13 SR 2154; 13 SR 2453; 16 SR 865; 18 SR 1059; 21 SR 1642; 23 SR 883; 25 SR 556; 25 SR 834; 28 SR 1086; 30 SR 1130

Statutory Authority: MS s 14.3895; 115.03; 116.07