Minn. R., Part 6132.4500

Current through Register Vol. 48, No. 51, June 17, 2024
Part 6132.4500 - SUSPENSION OF PERMIT TO MINE
Subpart 1.Procedure.

If an emergency situation arises that results in imminent danger, the commissioner, by written order to the permittee, may at that time suspend any portion or portions of operations as necessary to protect:

A. public health and safety;
B. public interests in lands and waters; or
C. persons and property.
Subp. 2.Requirements.

The commissioner shall require the permittee to take all measures necessary to prevent or remedy the emergency situation.

Subp. 3.Duration.

No suspension under this part shall be in effect more than 30 days without giving the permittee at least ten days' written notice of the order and an opportunity to be heard under part 6132.5000.

Minn. R., Part 6132.4500

17 SR 2207

Statutory Authority: MS s 93.44 to 93.51; 103G.222