Vegetation shall be established on the following:
Other vegetative measures shall be undertaken, as necessary, to:
The establishment of vegetation shall be initiated during the first normal planting period following the point when according to the permit to mine, a surface, structure, facility, or element is no longer scheduled to be disturbed or used in a manner that would interfere with the establishment and maintenance of vegetation, or after it has otherwise been required, using techniques such as grading, disking, or chisel plowing to reduce compaction, seeding or planting, fertilizing, mulching, and irrigating.
The following standards apply to the areas listed in subpart 1:
Minn. R., Part 6130.3600
Statutory Authority: MS s 93.47