Minn. R. agency 158, ch. 6115, PERMIT, INSPECTION, AND MONITORING FEES, pt. 6115.0060

Current through Register Vol. 49, No. 24, December 9, 2024
Part 6115.0060 - PERMIT FEES APPLICATIONS
Subpart 1.Fee.

A permit application fee of $75 shall accompany permit applications submitted under Minnesota Statutes, section 103G.271, appropriation and use of water, Minnesota Statutes, section 103G.531, subdivision 2, relating to dams, and Minnesota Statutes, section 105.391, relating to water bank.

Subp. 2.Protected waters; fee.

The permit application fee for works affecting protected waters, authorized under Minnesota Statutes, sections 103G.245 and 103G.297, shall be based on estimated project cost, the amount of material deposited in or removed from the protected waters, and the amount of shoreline affected by the project. The commissioner shall make the final determination of project costs used to calculate the permit application fee. The permit application fee shall be the greater of the fees calculated from the following parameter schedules, but not less than $75 nor more than $500:

A. Project cost parameter. If the project cost is greater than $7,500, the fee shall be one percent of the project cost. If a dispute arises between the commissioner and a permit applicant over project cost, the commissioner may require the permit applicant to submit a project cost estimate prepared by a registered professional engineer, contractor, planning consultant, or other qualified professional entity.
B. Shoreline affected parameter. If the project affects more than 100 feet of shoreline, the fee shall be 75 cents per foot of shoreline affected. For channel excavation projects, the shoreline affected is the difference in length in feet between the existing channel and the proposed channel.
C. Fill-excavation parameter. If the project requires more than 100 cubic yards of fill or excavation, the fee shall be 75 cents per cubic yard of material filled or excavated. For channel excavation projects, the volume in cubic yards is only that material filled or excavated in existing protected waters.
D. The permit application fee for protection of shoreline from erosion by placement of riprap and to recover shoreland lost by erosion or other natural forces, shall be limited to $75.
Subp. 3.Failure to remit.

If the permit application fee does not accompany the application, the applicant will be so notified. If no fee is received within 30 days from mailing of the written notice, the commissioner shall consider the application withdrawn and no further action shall be taken on it unless the applicant submits a new application accompanied by the minimum fee.

Subp. 4.Multiple applications.

If a project requires several permit applications, the permit application fee must accompany each application. Projects that involve a combination of work that results in both the alteration of protected waters and the use of waters of the state, shall be required to submit only one permit application and one set of fees. The type of permit application to be used and the fees to be charged shall be determined by the ultimate purpose of the project.

Subp. 5.Nonrefundable.

The permit application fee is not returnable, whether the application is permitted, modified, or denied, unless the commissioner determines the activity does not require a permit.

Subp. 6.Applications after commencement.

The permit application fee for permit applications filed after the work applied for has been partially or wholly completed, except for emergency work provided for in existing permit rules and policies, shall be double the amount that would have been charged if a timely application had been filed. In the case of a belated permit application, the permit application fee shall accompany the application or the commissioner shall proceed to issue a restoration order under Minnesota Statutes, section 103G.315, subdivision 7.

Subp. 7.Fees following a hearing.

If a hearing is demanded, and if the outcome of the hearing is a decision to issue a permit, payment of all required fees must precede issuance. The fee charged will be based on the schedules contained in this part regardless of whether a permit application has been filed.

Subp. 8.Form of payment.

Payment of all fees covered by parts 6115.0010 to 6115.0030, 6115.0060, 6115.0080 to 6115.0100, and 6115.0130 shall be made by check or money order payable to the Minnesota Department of Natural Resources. Cash cannot be accepted.

Minn. R. agency 158, ch. 6115, PERMIT, INSPECTION, AND MONITORING FEES, pt. 6115.0060

10 SR 236; 13 SR 2825

Statutory Authority: MS s 105.44; 103G.301; 103G.315