The public water supplier must submit a copy of the remaining portion of the wellhead protection plan to:
A public water supplier must allow 60 days for the governmental units identified in subpart 1 to comment in writing on the remaining portion of the wellhead protection plan.
A public water supplier must consider comments of a local unit of government, regional development commission, watershed district, or water management organization, if any, that:
A public water supplier must conduct a public hearing on the wellhead protection plan after the 60-day period for local review and comment is completed and before submitting the plan to the department.
Minn. R. agency 144, ch. 4720, PROCEDURES FOR WELLHEAD PROTECTION PLAN DEVELOPMENT AND REVIEW, pt. 4720.5350
Statutory Authority: MS s 103I.101