Before the remaining portion of the wellhead protection plan is prepared, a public water supplier must submit to the department:
No later than 60 days after the filing of the information specified in subpart 1, the department shall:
If a wellhead protection area delineation, a drinking water supply management area boundary, or a vulnerability assessment is disapproved, the department shall, as part of its notice of disapproval, provide the public water supplier with:
A public water supplier must revise a disapproved wellhead protection area delineation, drinking water supply management area boundary, or vulnerability assessment and submit the revision to the department within 45 days after receiving notice of disapproval.
On receipt of a revised wellhead protection area delineation, drinking water supply management area boundary, or vulnerability assessment, the department shall follow the same review process as for an original submittal.
Within 30 days of department approval, the public water supplier must submit a copy of the wellhead protection area delineation, the drinking water supply management area boundary, and the vulnerability assessments approved by the department to:
Within 60 days of the receipt of the notice of approval from the department, a public water supplier must hold one public information meeting for the general public about the approved:
Minn. R. agency 144, ch. 4720, PROCEDURES FOR WELLHEAD PROTECTION PLAN DEVELOPMENT AND REVIEW, pt. 4720.5330
Statutory Authority: MS s 103I.101