Minn. R. agency 144, ch. 4720, GENERAL WELLHEAD PROTECTION REQUIREMENTS AND CRITERIA, pt. 4720.5560

Current through Register Vol. 49, No. 29, 2025
Part 4720.5560 - IMPLEMENTATION OF APPROVED WELLHEAD PROTECTION PLAN
Subpart 1.Plan implementation.

A public water supplier must begin implementation of a plan no later than 60 days after the public water supplier has received department approval of the plan or amendments to the plan.

Subp. 2.Notification after plan adoption.

A public water supplier must notify local units of government within the drinking water supply management area of the adoption of a plan or amendments to a plan no later than 60 days after the public water supplier has received department approval of the plan or amendments to the plan.

Minn. R. agency 144, ch. 4720, GENERAL WELLHEAD PROTECTION REQUIREMENTS AND CRITERIA, pt. 4720.5560

22 SR 668

Statutory Authority: MS s 103I.101