Minn. R. agency 144, ch. 4658, NEW CONSTRUCTION; PLANS, pt. 4658.4030

Current through Register Vol. 49, No. 14, September 30, 2024
Part 4658.4030 - FINAL INSPECTION; NEW CONSTRUCTION

The department must be notified at least 30 days before the completion of construction so that arrangements can be made for a final inspection by the department and by the state fire marshal. Completion means the entire construction, equipment, staffing patterns, and services. Mechanical and electrical systems must be completed and tested for performance and safety in accordance with specifications and state requirements before new construction can be licensed and residents admitted.

Minn. R. agency 144, ch. 4658, NEW CONSTRUCTION; PLANS, pt. 4658.4030

21 SR 196

Statutory Authority: MS s 144A.04; 144A.08