The proposer of a renovation, replacement, or upgrading that is approved by the commissioner shall submit preliminary plans as defined in part 4660.0600 before drawing final plans.
The proposer of a renovation or replacement that is approved by the commissioner shall submit final architectural, mechanical, and electrical drawings as defined in parts 4660.0700 and 4660.0800 to the Minnesota Department of Health for review and approval before implementation of the project.
Changes in approved projects for renovation, replacement, or upgrading which alter the methods or materials described in the final working drawings must be submitted to the commissioner for review and approval before the changes are made, according to part 4660.0900.
If the commissioner approves the reported changes in a project, a change order permitting the changes shall be issued. The issuance of a change order does not alter the allowable costs as estimated in part 4655.1084, subpart 2.
The proposer shall immediately report to the commissioner any cost overruns including a description of the reasons for the overrun as required by Minnesota Statutes, section 144A.073, subdivision 3b.
On completion of the proposed project, the proposer shall submit to the Department of Human Services, a final statement of costs that includes a sworn statement of actual costs of items for which costs were estimated according to part 4655.1078, item G, and that compares the actual costs to the estimates.
Minn. R. agency 144, ch. 4655, PROCEDURES FOR EXCEPTIONS TO NURSING HOME BED MORATORIUM, pt. 4655.1098
Statutory Authority: MS s 144A.071; 144A.073