The board may impose reasonable and appropriate release permit conditions to mitigate or minimize the adverse impacts of the release on human health or the environment and to provide the board with information adequate to monitor compliance with the release permit and for analysis relating to future applications.
The application must be evaluated, and the draft release permit documents must be prepared, using an interdisciplinary approach that will ensure the integrated use of the natural and environmental sciences. The review shall include involvement of the following disciplines, as appropriate: microbiology, ecology, public health, biological safety, agronomy, plant biology, risk assessment, molecular biology, biochemistry, entomology, vertebrate biology, physical and biological containment, and other appropriate disciplines.
Within 45 days of acceptance of the application, the chair must prepare the draft release permit documents and publish notice of their availability in the EQB Monitor. The chair must provide a copy of the draft release permit documents to: each member of the EQB, the Environmental Conservation Library, the Legislative Reference Library, the regional development commission and regional development library for the region in which the release is proposed, governmental units with approval authority over the release, and local governmental units within whose boundaries the release is proposed, and any other person upon written request.
The board may order that the preparation and notice of the draft release permit documents be delayed for not more than 30 days if the application is for a release on multiple sites, for multiple years, or for organisms with different ecological impacts, or if the board determines that more time is needed to complete the preparation and notice of the draft release permit documents due to the complexity of the application.
The notice of the draft release permit documents must include, but is not limited to:
This notice may be combined with the notice of EAW availability required under part 4410.1500.
The chair must distribute the notice of the draft release permit documents in the following manner:
A 30-day period for review and comment on the draft release permit documents begins the day notice of the draft release permit documents is published in the EQB Monitor. Comments received after the close of the comment period need not be considered by the board.
Written comments may address the accuracy and completeness of the material contained in the application, potential impacts that may warrant further investigation before the release is approved, the adequacy of the draft release permit documents, additional permit conditions, and the need for a contested case hearing.
Written comments shall include the following:
One or more public meetings may be held during the public comment period to gather comments on the application and draft release permit documents if the chair determines that a meeting is necessary or useful. Public notice of the meetings shall be given prior to the meetings including mailed notice to persons registered pursuant to part 4420.0060, subpart 2, governmental units with approval authority over the release, and publication in a newspaper of general circulation in the county where the proposed release would take place. All meetings shall be open to the public.
The board must hold a contested case hearing when it finds all of the following:
When the board decides to hold a contested case hearing, the chair must prepare a notice of and an order for hearing, that includes:
The notice of hearing, distribution of the notice, and the conduct of the contested case hearing are governed by Minnesota Statutes, sections 14.57 to 14.62, and the rules of the Office of Administrative Hearings, parts 1400.5100 to 1400.8402.
The board shall review the record and issue, modify and issue, deny, or order a hearing on the release permit within 30 days of the close of the comment period unless:
Minn. R. agency 141, ch. 4420, pt. 4420.0030
Statutory Authority: MS s 116C.94